Production Switchers

 View Only
  • 1.  CC group hold

    Posted 09-28-2017 19:02
    I am using a custom control with a group hold on it and am using a separate CC to resume the group hold. I have found if the CC with the hold on it gets ran again (prior to being resumed), that will cause it to be resumed. Is this suppose to happen?


    Thanks,

    -Jason


  • 2.  RE: CC group hold

    Posted 09-28-2017 19:30
    Yes you are able to manually resume the held CCs. If you want to "re run" the CC you Should first STOP that CC and then run it again. You can add a STOP button as a function button just like all of the other function buttons. Then hold the STOP and press the CC you want to kill. If you want to kill all CCs that are running just double press the STOP button.
    #Vision


  • 3.  RE: CC group hold

    Posted 10-04-2017 20:51
    Thank you Les.
    #Vision