Graphics

 View Only
  • 1.  Questions about links Google Worksheet with DataLinq.

    Posted 10-16-2023 04:28
    I have a few questions during the test that links Google Worksheet with DataLinq.
     
    I added 'RSS/HTTP DataLinq Source' from 'Data Linq Server' and registered the URL of the Google worksheet to proceed.
     
    However, we have confirmed that the values are coming in normally, but we have confirmed that if you change the data in Google Worksheet, it will change in 2-3 minutes, not in real time.
     
    What I want is that when I change the data in Google Worksheet, I want the data to change in real time even within the XPN.
     
    When you add it in DataLinq, attach a picture of the configuration information and settings in the XPN.
     
    Is there anything that needs to be modified in the configuration?


    ------------------------------
    Dong-Geun Han
    Employee
    Youngdo B&C
    [Seoul] [Republic of Korea]
    ------------------------------


  • 2.  RE: Questions about links Google Worksheet with DataLinq.

    Posted 10-25-2023 11:37

    Are you using XPression v11.5?